South American Oil Refinery

Americas

HKA

ICC Arbitration Panel awards contractor only 20% of its claim

What we did

HKA was retained by counsel on behalf of the owner of an oil refinery in South America to rebut claims in excess of US$50 million brought by the civil contractor. The claims for increased costs related to purported delay and disruption caused by late design information during the refinery expansion project.

HKA authored two-200 plus page reports and testified on schedule delay and damages issues at the ICC arbitration proceedings.

Outcomes

The tribunal awarded the civil contractor only US$10.8 million of its US$50 million claim, not including prejudgment interest.

Project Details
  • Client
    Confidential
  • Year
    2017
  • Value
    US$50 million
  • Services
    Delay and Disruption Analysis
  • Sectors
    Construction and Engineering, Oil and Gas