Acceleration of construction projects
7th February 2024
Acceleration of construction projects[1]For a more comprehensive review of this topic see Mastrandrea, F, “The Appraisal of Contractors’ Acceleration Claims”, [2024] ICLR 27.
Acceleration is increasingly on the agenda for construction projects. Its use for decades in the U.S in the form of constructive acceleration appears to continue unabated, and there is some evidence that the concept may be sought to be applied more broadly in other jurisdictions.
Acceleration can be achieved in a variety of ways: by changing the design or specification of permanent and/or temporary works, altering methods of working, re-sequencing work, introducing additional (or more expensive) resources whether material plant or labour, working overtime, extending working hours, introducing shift working, etc.
The SCL ‘Delay and Disruption Protocol’, Second Edition, 2017, defines acceleration by reference exclusively to contractor-driven strategies.
Although acceleration has traditionally been discussed in the context of project, or critical path, delays, that seems too narrow a focus. The underlying justification for acceleration claims can, it is suggested, be put more broadly: the contractor’s wish through acceleration to contain its costs or losses, or increase its profit. Thus, a contractor hindered by defaults of the employer which lead to non-critical delays would typically be entitled, as a remedy for breach of contract, or according to the contract’s loss/expense provisions, to localised time-sensitive and/or disruption costs.[2]For a more comprehensive review of this topic see Mastrandrea, F, “Localised Delays: The Poor Relation in Construction Claims Appraisals?”, [2023] ICLR 112. The contractor sees advantage in those circumstances in taking exceptional accelerative measures as a potential means of reducing overall costs it incurs, and claims additional expenditure in pursuing that acceleration, and proves that expenditure (which can in all cases of acceleration be a challenging task, being an exercise in incremental costing). If that is right, acceleration is not confined to seeking to reduce the duration of critical path activities.
Acceleration directed at some failure on the part of the employer, is to be distinguished from acceleration motivated by some other consideration. A contractor making poor progress (for whatever reason) will often find itself under significant pressure from an employer to improve upon that progress. The additional cost of accelerative measures taken in response to legitimate demands by an employer for the contractor to pick up the pace of works will typically be unrecoverable.
By contrast, additional costs incurred by a contractor instructed or directed to accelerate where the contractor is not itself falling behind will typically be recoverable.
It seems unlikely that, in the absence of an express provision to that effect, an obligation on the part of the contractor to accelerate arises simply by reason of the application of common-sense principles, as presumably the contractor will ordinarily be entitled to say that if it is late in completion the employer will have its remedy in delay damages.
Constructive acceleration, widely recognised in the U.S., is intended to denote deemed, as opposed to instructed, acceleration. Notwithstanding some recent suggestions otherwise in response to unfolding case law,[3]A recent example popularly used for illustration is V601 v. Probuild [2021] VSC 849. it has not found fertile ground in other common law jurisdictions[4]There appear to be few examples of the concept being pursued in civil law jurisdictions: for an exception, see the ‘accélération par induction’ in Dawcolectric inc. c. Hydro-Québec, 2014 QCCA … Continue reading where, beyond instructed acceleration, compensation is typically limited to accelerative measures taken by way of a justifiable response, such as mitigation, to a breach of contract. The challenge then becomes one of identifying the triggering breach. This is typically a failure on the part of the employer or its agents properly to discharge its contractual obligations (e.g. to grant possession of the site, to provide timely design information, by the contract administrator to carry out the employer’s functions, or illegitimate collusion with the employer such as by failing to award extensions of time properly due).
As with other claims a contractor’s claim for acceleration may be barred because of its failure to submit its claim in accordance with the express contractual requirements, many of which may be exacting, although exceptions, such as waiver and the employer’s own knowledge, may apply in particular jurisdictions.
A disincentive to acceleration may in future be the increasing availability – by way of developing standard forms of contract and/or statutory reforms – of adjudication or other expedited forms of dispute resolution to decide delay claims speedily.
About the Author
Franco Mastrandrea is a Chartered Quantity Surveyor and Chartered Arbitrator with over 40 years of experience in the construction industry. He has acted as expert on more than 50 international project management, delay and quantum-related disputes.
HKA Services
HKA is a leading global consultancy in risk mitigation, dispute resolution, expert witness and litigation support services.
We collaborate with various stakeholders including owners, operators, contractors, subcontractors, law firms and government agencies, tailoring our services to meet their individual requirements.
Contact us to enquire about our market-leading expert services.
References
↑1 | For a more comprehensive review of this topic see Mastrandrea, F, “The Appraisal of Contractors’ Acceleration Claims”, [2024] ICLR 27. |
---|---|
↑2 | For a more comprehensive review of this topic see Mastrandrea, F, “Localised Delays: The Poor Relation in Construction Claims Appraisals?”, [2023] ICLR 112. |
↑3 | A recent example popularly used for illustration is V601 v. Probuild [2021] VSC 849. |
↑4 | There appear to be few examples of the concept being pursued in civil law jurisdictions: for an exception, see the ‘accélération par induction’ in Dawcolectric inc. c. Hydro-Québec, 2014 QCCA 948. |
This publication presents the views, thoughts or opinions of the author and not necessarily those of HKA. Whilst we take every care to ensure the accuracy of this information at the time of publication, the content is not intended to deal with all aspects of the subject referred to, should not be relied upon and does not constitute advice of any kind. This publication is protected by copyright © 2024 HKA Global Ltd.